• Client: Ogun State Water Corporation
  • Value of the works: US$8,155,072.87
  • Start Date: June, 2019
  • Duration of the works: 9 Months

Distribution Network in Ilesa

Distribution Network in Ilesa East Zone, Lot2 (Contract No: IWP/2016/008B)

Description of the works:
Supply, Butt-fused and laya total of PE 100 pipes including house connections and communal water:

  • 50mm-49,817m
  • 63mm-32,541m
  • 110mm-108,254m
  • 160mm-25,810m
  • 200mm-22,224m
  • 315mm-5,491m
  • Fire Hydrants – 139, Air Valves – 34, Washout – 37, House Connections – 9,384
    Communal Stand pipes – 24
    Value of the works:
    StartDate:JUNE2019
    Durationoftheworks:9MONTHS